The top management was feeling that when there are any
changes in the technology being used, development schedules etc, it was a
waste of time to update the Test Plan. Instead, they were emphasizing that
you should put your time into testing than working on the test plan. Your
Project Manager asked for your opinion. You have argued that Test Plan is
very important and you need to update your test plan from time to time.
It’s not a waste of time and testing activities would be more effective
when you have your plan clear. Use some metrics. How you would support
your argument to have the test plan consistently updated all the time.
-
The QAI is starting a project to put the CSTE
certification online. They will use an automated process for recording
candidate information, scheduling candidates for exams, keeping track of
results and sending out certificates. Write a brief test plan for this new
project.
-
The project had a very high cost of testing. After
going in detail, someone found out that the testers are spending their
time on software that doesn’t have too many defects. How will you make
sure that this is correct?
-
What are the disadvantages of overtesting?
-
What happens to the test plan if the application has a
functionality not mentioned in the requirements?
-
You are given two scenarios to test. Scenario 1 has
only one terminal for entry and processing whereas scenario 2 has several
terminals where the data input can be made. Assuming that the processing
work is the same, what would be the specific tests that you would perform
in Scenario 2, which you would not carry on Scenario 1?
-
Your customer does not have experience in writing
Acceptance Test Plan. How will you do that in coordination with customer?
What will be the contents of Acceptance Test Plan?
-
How do you know when to stop testing?
-
What can you do if the requirements are changing
continuously?
-
What is the need for Test Planning?
-
What are the various status reports you will generate
to Developers and Senior Management?
-
Define and explain any three aspects of code review?
-
Why do you need test planning?
-
Explain 5 risks in an e-commerce project. Identify the
personnel that must be involved in the risk analysis of a project and
describe their duties. How will you prioritize the risks?
-
What are the various status reports that you need
generate for Developers and Senior Management?
-
You have been asked to design a Defect Tracking system.
Think about the fields you would specify in the defect tracking system?
-
Write a sample Test Policy?
-
Explain the various types of testing after arranging
them in a chronological order?
-
Explain what test tools you will need for client-server
testing and why?
-
Explain what test tools you will need for Web app
testing and why?
-
Explain pros and cons of testing done development team
and testing by an independent team?
-
Differentiate Validation and Verification?
-
Explain Stress, Load and Performance testing?
-
Describe automated capture/playback tools and list
their benefits?
-
How can software QA processes be implemented without
stifling productivity?
-
How is testing affected by object-oriented designs?
-
What is extreme programming and what does it have to do
with testing?
-
Write a test transaction for a scenario where 6.2% of
tax deduction for the first $62,000 of income has to be done?
-
What would be the Test Objective for Unit Testing? What
are the quality measurements to assure that unit testing is complete?
-
Prepare a checklist for the developers on Unit Testing
before the application comes to testing department.
-
Draw a pictorial diagram of a report you would create
for developers to determine project status.
-
Draw a pictorial diagram of a report you would create
for users and management to determine project status.
-
What 3 tools would you purchase for your company for
use in testing? Justify the need?
-
Put the following concepts, put them in order, and
provide a brief description of each:
-
What are two primary goals of testing?
-
If your company is going to conduct a review meeting,
who should be on the review committe and why?
-
Write any three attributes which will impact the
Testing Process?
-
What activity is done in Acceptance Testing, which is
not done in System testing?
-
You are a tester for testing a large system. The system
data model is very large with many attributes and there are a lot of
inter-dependencies within the fields. What steps would you use to test the
system and also what are the effects of the steps you have taken on the
test plan?
-
Explain and provide examples for the following black
box techniques?
-
Boundary Value testing
-
Equivalence testing
-
Error Guessing
-
What are the product standards for?
-
You are the test manager starting on system testing.
The development team says that due to a change in the requirements, they
will be able to deliver the system for SQA 5 days past the deadline. You
cannot change the resources (work hours, days, or test tools). What steps
will you take to be able to finish the testing in time?
-
Your company is about to roll out an e-commerce
application. It’s not possible to test the application on all types of
browsers on all platforms and operating systems. What steps would you take
in the testing environment to reduce the business risks and commercial
risks?
-
In your organization, testers are delivering code for
system testing without performing unit testing. Give an example of test
policy:
-
Policy statement
-
Methodology
-
Measurement
-
Testers in your organization are performing tests on
the deliverables even after significant defects have been found. This has
resulted in unnecessary testing of little value, because re-testing needs
to be done after defects have been rectified. You are going to update the
test plan with recommendations on when to halt testing. Wwhat
recommendations are you going to make?
-
How do you measure:
-
Test Effectiveness
-
Test Efficiency
-
You found out the senior testers are making more
mistakes then junior testers; you need to communicate this aspect to the
senior tester. Also, you don’t want to lose this tester. How should one go
about constructive criticism?
-
You are assigned to be the test lead for a new program
that will automate take-offs and landings at an airport. How would you
write a test strategy for this new program?